Nevada Copper Corp.

Pumpkin Hollow

Development Program

2007
  • Completed $7 Million, 19,000 meter infill and step out drilling program.
  • Assayed/Re-Assayed over 5100 meters of historic core not previously assayed for copper, gold, silver and molybdenum.
  • Expanded land package to 5700 contiguous hectares (22 square miles)
2008
  • Preliminary Economic Assessment (PEA) completed in March demonstrating positive Project economics.
  • Executed $9 Million, 26,000 meter infill and step out mineral, geotechnical and metallurgical drilling program.
  • Assayed/Re-Assayed over 12,000 meters of historic core and rejects for Cu, Au, Ag and Mo.
  • Permitting, metallurgical, hydrological and geotechnical studies/activities to support Feasibility.
2009
  • Completed updated Resource Estimate incorporating results from 2008 drilling program.
  • Commenced Project Feasibility.
  • Continue collecting baseline data to support Feasibility and Permitting.
  • Select geotechnical and in-fill drilling to support Feasibility.
2010
  • Refine metallurgical testwork
  • Further detailed evaluation of iron deposit
  • 50,000 meter drilling program - expanded
2011
  • Secured Underground Access Permit by Q1 2011
  • Commence permitting Phase 1 - private land U/G mine
  • Definitive Feasibility - started Q4 2010
  • Commence Advanced Exploration Program
2012 Objectives
  • Optimized Feasibility Study
  • Definitive Feasibility Study(complete -- January 2012)
  • Decision on Land acquisition from Federal Government by the City of Yerington (in progress)
  • Updated Resource/Reserve to incorporate plus 50,000 meters of drilling since November 2010 (released September 7, 2012)
  • Feasibility Study on Stage 1 Private Land Underground Mine
  • Submit project permitting documents to State (Completed August 2012)
  • Construction - underground east shaft (started)
  • Execute strategic partnership (discussions in progress)
2013 Objectives
  • Optimized Feasibility Study
  • Receive State development permits for either Private Land Underground Mine "PLUM" and/or Integrated open pit operations
  • Complete shaft sinking to total depth
  • Execute a mine financing package or strategic investment to allow for mine construction
  • Commence mine construction for either the PLUM or Integrated open pit/underground operations